Indian Space Program: News & Discussions

  • Thread starter Thread starter Tarun
  • Start date Start date
  • Tags Tags
    isro
A Major Milestone has been reached!

Written by [email protected]
12 November 2024

The team has excelled themselves in completing all the stand alone testing required in the SP-1B facility allowing for the transfer of the satellites to the SP-2B facility where the CSC satellite will undergo a fit check with the launcher payload adapter (PLA) prior to the start of the fuelling activities.

1731519035076.png

The satellites were packed ready to be loaded on the trucks.

DSCN7692-2048x1536.jpg

The satellites arrived in SP-2B, were allowed to acclimatise overnight in the airlock and today had their lids removed to allow them to be pushed into the cleanroom.

The team then had a rest to gain energy for the fit check with the LVA

DSCN7708-2048x1536.jpg

The CSC spacecraft was then lifted and moved over to be mounted on the LVA.

1731518886285.png

And then carefully lowered and mated on the LVA. The clampband holding the two together was then installed to ensure a perfect fit.

DSCN7780-scaled.jpg

With the CSC spacecraft mated on the LVA the umbilical cables allowing the spacecraft to be monitored during fueling and launch were installed and tested to ensure they connected and, importantly, disconnected when the clampband opened and the satellite separated from the LVA.

DSCN7816-scaled.jpg

With the checks completed the team was able to have some food and well earned rest.

The team also said farewell to some colleagues but welcomed others arriving today.

A Major Milestone has been reached! – Proba-3 blog
 
  • Like
Reactions: TARGET
ISRO's current R&D thrust:
1732158115661.png

Concept of the 3rd launch pad at SHAR & the new SSLV pad at Tuticorin:
1732158190895.png

Quantum comms R&D is moving towards operationalization:
1732158322044.png

NavIC constellation is set to expand:
1732158340298.png

ISRO plans to make 60+ LVM3 launchers over the next decade or so:
1732158646150.png

Snip off tech transferred from ISRO to various industry:
1732158682235.png
 
  • Like
  • Informative
Reactions: Ashwin and Parthu
Exo-worlds mission is shaping up. Apparently, this will get a JWST like segmented mirror telescope. Also, like the JSWT this telescope will also be place at L2:
1732297398801.png
If it ends up weighing as much as the JWST, then we will need the NGLV to launch this.
 
  • Like
Reactions: Parthu
A Major Milestone has been reached!

The next phase

Written by [email protected]
16 November 2024

With the satellites tested and fit for flight the team from ArianeGroup are here to perform the propulsion activities starting with checking the the integrity of the subsystems and finishing with the hydrazine fueling of the CSC satellite.

Here you can see the setup and execution of the ongoing pressurization activities.

DSCN8016-2-2048x1536.jpg
DSCN8025-2048x1536.jpg
DSCN8038-2048x1536.jpg

And once the pressure exceeded a certain safety limit extra protection was required by the team.

DSCN8050-2048x1536.jpg

Under Pressure!!

The ArianeGroup fueling team have done an amazing job testing both satellites and filling the OSC with 268 bar of nitrogen for flight. The CSC was pressurised to MEOP to allow leak testing to be performed.

During the activities what we could see from the control room looked like a SWOT team had raided the facilities.

DSCN8063-scaled.jpg

Leak testing has its challenges…..especially wearing a bullet proof vest and helmet!

DSCN8074-2048x1536.jpg
DSCN8087-scaled.jpg
DSCN8084-2048x1536.jpg

Also, earlier in the day the two hydrazine drums were delivered to the facility for acclimatization in preparation for fueling.

DSCN8105-2048x1536.jpg
 
Satellite Stacking

With the OSC being successfully fueled and the final preparation activities completed the satellites could be stacked as they are installed on the launcher already attached to one another and it is only during commissioning that the clampband holding the satellites together is released and they separate.

In preparation the upper cone from the CSC was removed and fitted to the vertical integration stand allowing the OSC to be lowered on to it and the clampband fitted.

IMG_0910-2048x1365.jpg
IMG_0918-2048x1365.jpg

The OSC, clampband and cone was then lifted and lowered onto the CSC where the cone and umbilicals could be installed and mated.

IMG_1031-2048x1365.jpg
IMG_1103-scaled.jpg

IMG_1142-scaled.jpg

The stacked satellites were then transferred back to the vertical integration stand in preparation for the next important activity, the hydrazine fueling of the CSC, after which the satellites will be ready to be transferred to the launcher in SP3.

IMG_1185-scaled.jpg

It was a long day for the team who did a remarkable job stacking the satellites. Now off back to the guest house for a well earned meal.

IMG_1173-2048x1365.jpg

Satellite Stacking – Proba-3 blog
 
Fully Loaded!

Written by [email protected]
23 November 2024

Today the team came in early to start the preparations for fueling of the CSC satellite. The safety officer checked all the setup was safe and the hydrazine drum was moved into the fueling hall and placed on the scales.
DSCN8930-scaled.jpg
DSCN8931-2048x1536.jpg
The fueling team tried on the new SCAPE suites for size. Apparently, they are unisex :-)
DSCN8941-scaled.jpg
The setup was completed, and the team were ready to start.
DSCN8932-1536x1152.jpg
The fueling team put on their SCAPE suites, entered the fueling hall and started activities. This is the view the team in the control got whilst monitoring the activities.
DSCN8943-2048x1536.jpg
Final activities and a happy pair of operators.
DSCN8944-1536x1152.jpg
DSCN8949-scaled.jpg
The fueling of the CSC satellite was successfully completed just leaving pressurisation in the morning. Another very professional fueling program by the ArianeGroup team. The team was also very pleased to hear the news.
STACK-DINNER-CELEBRATION-scaled.jpg

Fully Loaded! – Proba-3 blog
 
Ready for Combined Operations!

Written by [email protected]
24 November 2024

The final pressurization has been performed on the CSC and the valves capped and locked.
DSCN8985-2048x1536.jpg
The satellite is ready to go to the next phase of the launch campaign, Combined operations where activities are now performed with the launcher team starting with mating on the PLA.

Things were tidied up and some pictures taken.
DSCN9009-2048x1536.jpg
DSCN9014-2048x1536.jpg
As most of the team were not involved in the fueling, they enjoyed a boat trip to a local island.
36be426a-249b-4dc9-9555-05a53cb20c52.jpeg
WhatsApp-Image-2024-11-24-at-14.16.40.jpeg

Ready for Combined Operations! – Proba-3 blog
 
Move to the Launch Pad

Written by [email protected]
25 November 2024

Today was meant to be a leisurely day of tidying up the satellites, mating on the PLA and moving into the transport container ready for a move to the launch pad tomorrow. Well due to severe weather warnings it was decided to move today so all hands to the pump.

The close out activities were completed on the satellites and the solar arrays checked. A cover was then put on the stack to protect it in the container.

The stack was then mated onto the PLA
DSCN9089-2048x1536.jpg
The clamp band and umbilicals were then installed before the stack was moved to the container.
DSCN9104-2048x1536.jpg
DSCN9120-2048x1536.jpg
The adapter was bolted to the base and the lid installed, a scary place for the two satellites.
DSCN9147-scaled.jpg
Once closed the container was transferred to the waiting lorry to take it to SP3.
DSCN9183-2048x1536.jpg
Before the lorry could leave there were a couple of interesting traditions to perform. One was lemons under the wheels 🍋 , which is considered to absorb negative energies, is crushed as the vehicle moves forward, signifying the destruction of any evil forces or bad luck. This ritual is believed to purify the vehicle, ensuring smooth, accident-free journeys and the other was breaking open coconuts. It is believed that doing this helps in keeping the problems away and makes the work successful.
DSCN9191-1536x1152.jpg
DSCN9224-2048x1536.jpg
Then the move to SP3
DSCN9255-scaled.jpg
The journey took about 50min and some of the team walked with it for the last part. The service tower doors were open and a very impressive launch waiting to receive its passenger.

More pics to follow.

Move to the Launch Pad – Proba-3 blog
 
  • Haha
Reactions: TARGET
One step closer

Written by [email protected]
28 November 2024

The satellites stayed in its transport container whilst clean room conditions were re-established and monitored to ensure the cleanliness of the satellites is maintained.

Once satisfied the lid could be removed and the activities performed prior to transferring the stacked satellites onto the launcher. With preparations done there was a briefing before the mating.

A41I1409-2048x1365.jpg

And a well-deserved group picture with the stack safely installed on the launcher.

A41I1629-scaled.jpg

One step closer – Proba-3 blog