F
Falcon
Sir.
Let us analyze this write up.
First fallacy.
The IAF fixed the ASQR and formalised it, handing over the QR to ADA-HAL and Project LCA in October 1985, the primary QR being of aircraft being ready for induction by 1993.
By 1993, 54 permanent waivers of critical nature were agreed to by IAF, thereby diluting the ASQR, in order to enable the aircraft to enter into IAF colors. Yet, the same was never achieved.
Since the very first post is based on twisting of facts, and facts remain a premium in the world of fake and planted news, need we even analyze further?
Let me continue. It is interesting to note, and here many should, in order to understand the criticism that the Project draws, that the author has tried to contend that IAF kept on revising it's QR.
Yes, indeed it did, by diluting it!
And whose mistake was that? IAF's? In the meanwhile, IAF was expected to carry on with legacy aircrafts of Mig-21s manufactured in 60s and 70s with an airframe life slated for 25 years? Strange logic.
Let us recall that GTRE was confident of delivering a Kaveri by 1993.
Interesting. And so, indigenous bogey is incorrect? A contradiction.
Remaining can be discussed later.
Let us analyze this write up.
False Argument 1: The Tejas is “late”. It has been under development for 32 years!
The figure is technically true, but deprives the narrative of much-needed context. The Tejas’ origins can indeed be traced back to 1983, when the concept of a Light Combat Aircraft (LCA) was conceived. However, the IAF did not finalise its air staff requirements (ASRs) until 1985 (and kept on requesting major changes throughout the design and development phase, but more on that later)
First fallacy.
The IAF fixed the ASQR and formalised it, handing over the QR to ADA-HAL and Project LCA in October 1985, the primary QR being of aircraft being ready for induction by 1993.
By 1993, 54 permanent waivers of critical nature were agreed to by IAF, thereby diluting the ASQR, in order to enable the aircraft to enter into IAF colors. Yet, the same was never achieved.
Since the very first post is based on twisting of facts, and facts remain a premium in the world of fake and planted news, need we even analyze further?
Let me continue. It is interesting to note, and here many should, in order to understand the criticism that the Project draws, that the author has tried to contend that IAF kept on revising it's QR.
Yes, indeed it did, by diluting it!
and initial funding did not come through until 1986. The project definition phase — the phase in which technical requirements are defined and a conceptual design prepared did not end until 1988. The final design was completed in 1990. Full funding was issued only in 1993, after which the development of a prototype commenced in earnest. Source.
And whose mistake was that? IAF's? In the meanwhile, IAF was expected to carry on with legacy aircrafts of Mig-21s manufactured in 60s and 70s with an airframe life slated for 25 years? Strange logic.
Let us recall that GTRE was confident of delivering a Kaveri by 1993.
Following several years of delay in the development process — delays that can at least partly be traced backto US sanctions on India following the 1998 nuclear tests — the Tejas had its first flight in 2001.
Interesting. And so, indigenous bogey is incorrect? A contradiction.
Remaining can be discussed later.